Mortar Calculator

A 200 square foot wall of modular brick takes 1350 brick and 11 cubic feet of mortar at a 3/8 inch joint — 1418 brick and 11.55 cubic feet once your 5 percent for waste goes on. Masonry sand matches the mortar, cubic foot for cubic foot.

Sheet A-202
Discipline Architectural
Revised
Formula rev. 1.0.0
Checked against 1 source

Units available: US customary / metric.

Wall, openings, brick size and joint

Enter a length in the selected unit, or type feet and inches.

Type 25, 25 ft 6 in or 25' 6″. Measure the face of the wall, corner to corner.

Enter a length in the selected unit, or type feet and inches.

Top of the ledge or footing to the top of the brickwork. Courses are not rounded: order by area.

Order options

Nominal sizes, the joint already inside them — Modular 4 x 2-2/3 x 8 · Engineer Modular 4 x 3-1/5 x 8 · Closure Modular 4 x 4 x 8 · Roman 4 x 2 x 12 · Norman 4 x 2-2/3 x 12 · Engineer Norman 4 x 3-1/5 x 12 · Utility 4 x 4 x 12. Specified sizes, the unit itself — Queen 2-3/4 x 2-3/4 x 7-5/8 · King 2-3/4 x 2-5/8 x 9-5/8 · Standard 3-5/8 x 2-1/4 x 8 · Engineer Standard 3-5/8 x 2-13/16 x 8.

The joint selects a column of quantities. It is never added on top of the brick, least of all a nominal one.

5 % to start, and it is your allowance, not a published one: the quantities behind this sheet are a theoretical volume of mortar in the wall with no waste at all.

Turn this on if the brick are already counted off your plans. The mortar is then read per 1,000 brick instead of per 100 square feet, and the takeoff line says so.

Advanced: doors, windows and other openings (deducted), hollow brick, and the yield on your own bag, prices you were quoted

Doors, windows and other openings (deducted)

Enter a length in the selected unit, or type feet and inches.

Rough opening, out to out. The count multiplies it. Sills, lintels and jamb brick come off your plans.

Enter a length in the selected unit, or type feet and inches.

Rough opening height. Blank or 0 leaves this opening out.

How many openings of this size.

Enter a length in the selected unit, or type feet and inches.

A second opening type — a window against a door, say.

Enter a length in the selected unit, or type feet and inches.

Rough opening height for the second type.

How many openings of the second size.

Hollow brick, and the yield on your own bag

Hollow brick bedded on the face shells only, as structural work usually is. This takes mortar off and leaves the brick count alone.

Read it off the bag you are buying. Nothing we opened publishes a yield for preblended mortar, so blank means no bag count rather than a figure we invented.

Prices you were quoted

Leave blank to skip. Shelf or yard price of one bag of the mix you are buying.

Brick is quoted by the unit, by the cube and by the thousand; type the price of one.

JavaScript is off, so this sheet shows its worked example only. Turn it on to calculate with your own numbers.

Brick to order1,418ea

Order 1,418 ea

Brick in the wall
1,350 ea
Mortar volume
11.55 cu ft
Masonry sand
11.55 cu ft
Wall area
200 sq ft
  • NoteNothing we opened publishes how much mortar a bag of preblended mix yields. Type the cubic feet per bag from your bag's label and the sheet counts bags.

Drawings

A-202
Dimensioned elevation of the brick wallWall 25'-0″ long by 8'-0″ high in half-brick bond, 1,418 brick to order at a 3/8 inch joint.1,418 BRICKMORTAR 11.6 CFRUNNING BONDPER 100 SQ FT
Detail of a bed joint and a head jointTwo courses of brick in half-brick bond showing the horizontal bed joint and the vertical head joint at 3/8″ joint. The joint thickness selects a column of the published table; it is never added to the size of the brick.JOINT = COLUMNNOT ADDED ONTO BRICK SIZEJOINT NTS

Takeoff

A-202 — material takeoff
Item Net qty Waste Order
Modular brick, 3/8 in jointTable 4, Modular, 3/8 in joint: 675 brick and 5.5 cu ft of mortar per 100 sq ft of wall. 200 sq ft net gives 1,350 brick, plus 5%, rounded up.1,350 ea5%1,418 ea
Mortar in the wall, 3/8 in jointTable 4, Modular, 3/8 in joint: 675 brick and 5.5 cu ft of mortar per 100 sq ft of wall. That volume excludes waste of any kind. Your 5% allowance is applied after it.11 cu ft—11.55 cu ft
Masonry sand, loose and dampThe source: 1 cubic foot of loose, damp sand yields about one cubic foot of mortar. So this wall takes as many cubic feet of sand as of mortar. No weight: no density is published for it here.11.55 cu ft—11.55 cu ft
Assumptions used
  • Brick and mortar read from the 100 sq ft column of the table: 675 brick and 5.5 cu ft per 100 sq ft for Modular at a 3/8 in joint.
  • The table rounds its per-100-sq-ft and per-1,000-brick columns separately, so the same wall differs by about half a percent between them. This sheet names the basis it used and never mixes the two.
  • The joint selects a column, it is not added to the brick: this size is listed at its nominal dimensions, which already contain the joint.
  • Waste and breakage 5%: your own allowance. The published quantities are a theoretical volume of mortar in the wall and contain no waste at all.
  • Solid bedding assumed. Hollow brick laid in face-shell bedding takes less mortar - turn the toggle on and type the voids in your unit.
  • Sand is one cubic foot of loose, damp sand per cubic foot of mortar, the source's own rule. The sheet stops at volume: no sand weight and no tonnage is published for it here.
  • No bag count until you type the cubic feet per bag from your label: nothing we opened publishes a yield for preblended mortar, and the eight-bags-per-1,000-brick trade rule is called a very rough estimate by the association that publishes it.
  • Running or stack bond, single wythe. Patterns with headers, collar joints, chimneys and repointing take more mortar and are not counted here. Mortar type M, S, N or O changes the materials, not these volumes.
Order1,418 ea

One form: the wall, the brick, the mortar

Most mortar calculators start where this one finishes: the only masonry takeoff page in the measured top six wants a brick count you do not have yet. Here the wall goes in once — length, height, openings — and brick, mortar and sand come out together, in US customary units or metric. That switch is on no readable page of the six.

The quantities come from one document, the brick industry’s own estimating note, and its sentence is careful: Table 4 presents the estimated quantities of brick and mortar (not including waste) required for brick masonry according to the size of brick used in the wall. The mortar quantities are based on theoretical dimensions of the mortar in the wall. Not including waste, and theoretical — so the allowance here is your field, opening at 5 percent. At zero this wall orders 1350 brick instead of 1418. None of the calculators we could read cites anything.

Eight bags per 1,000 brick

There is a trade rule for mortar, and the ranking calculators are built on it. It is the sentence just before the one above: Masons frequently use a rule of thumb that eight bags of masonry cement will lay 1000 modular brick. This is a very rough estimate and includes an unspecified amount of waste.

Why this sheet does not use it. A figure its own publisher calls very rough, with an unspecified amount of waste already inside, is not one you can order against. The warning is quoted here; the rule is never computed with.

It reads a published volume instead, by brick size and joint, in two columns: per 100 square feet, or per 1,000 brick when you have a count. Each is rounded on its own, so they disagree — 1,000 modular brick at 3/8 inch is 8.1 cubic feet one way, 8.148 the other, 0.59 percent apart. The takeoff line names the basis it read.

The joint picks a column, it is not added on

A modular brick is listed at its nominal size and the joint is already inside it: four inches of module is the brick plus its joint. So the 3/8 or 1/2 inch choice selects which published quantities to read, and adding the joint on top counts the same mortar twice. The column matters — this wall goes from 11.55 cubic feet at 3/8 inch to 14.49 at 1/2 inch, with the brick count unmoved. Queen, King, Standard and Engineer Standard are the exception the field names: specified dimensions, the unit itself, and the joint still selects a column.

Sand, cubic foot for cubic foot

Sand has a rule of its own: The commonly used “rule of thumb” is appropriate: 1 cubic foot (cubic meter) of loose, damp sand will yield about one cubic foot (cubic meter) of mortar. The sand line therefore equals the mortar line, 11.55 cubic feet here. This sheet stops at volume: the source publishes no density for masonry sand, so no weight and no tonnage is printed here. By the ton, take the volume to C-103.

Hollow brick, face-shell bedded

Structural hollow brick is usually bedded on the face shells, and the quantities may come down by the voids in the unit — typically 25 to 35 percent. The toggle applies your figure to the mortar and nothing else: at 30 percent this wall drops from 11.55 to 8.09 cubic feet and still orders 1418 brick.

Type M, S, N or O

The type changes what goes in the mixer, not how much the wall swallows: the volumes above hold whichever one you specify. The proportions live in the specification this note points to, ASTM C270, and are not reprinted here: choosing between the types is a job for your plans and your local code.

Sheet A-202 formula
Net      An =  L x H - sum( w x h x count )   (sq ft)
Brick    B  =  An / 100 x per100(size)
Order    Bo =  ceil( B x (1 + waste / 100) )
Mortar   Mv =  An / 100 x per100cf(size, joint)
or       Mv =  N / 1000 x per1000cf(size, joint)
Bedded   Mb =  Mv x (1 - voids / 100) x (1 + waste / 100)
Sand     Sv =  Mb                        cu ft for cu ft
Bags     Bg =  ceil( Mb / yield )        from your label
per100
Brick per 100 sq ft: 675 in modular.
joint
3/8 or 1/2 in. It picks a column, never adds one.
waste
Opens at 5, and it is yours.

Worked example: a 40 foot facade with four openings

Forty by nine feet, three 3 by 5 foot windows and a 3 by 7 foot door, modular brick, 3/8 inch joint, 5 percent.

  1. Gross 360 sq ft, less 66 of openings: 294 sq ft net.
  2. Brick: 1985 in the wall, 2084 to order.
  3. Mortar: 16.17 cu ft in the wall, 16.98 to buy.
  4. Sand: 16.98 cu ft, loose and damp.

Frequently asked

How do you calculate how much mortar you need?
From wall area, or from a brick count. This 200 square foot wall of modular brick takes 11 cubic feet at a 3/8 inch joint, 11.55 with your 5 percent on it; at 1/2 inch, 14.49.
How many square feet will a 50 lb bag of mortar cover?
We do not guess at it. Nothing we opened publishes how much mortar a 50, 60 or 80 lb bag of preblended mix yields, so the bag count stays blank until you type the cubic feet per bag from your own bag's label. Type it in and the sheet counts bags.
How much mortar calculator?
This one, free. Brick size, joint, wall or count in; brick, mortar, sand and bags out, with the arithmetic shown.
Should I use type S or type N mortar?
Type N is the general-purpose mortar for above-grade veneer; type S is specified where the wall takes more lateral load or sits below grade. The proportions are the standard's, and are not printed here.

Limits of this sheet

A-202 turns a brick elevation into a count, a mortar volume and the sand to match, from one published set of quantities — read it at BIA Technical Note 10. Single wythe, running or stack bond: header patterns, collar joints, chimneys, repointing and stonework take more mortar. Laying concrete block? The block sheet counts the units and their mortar — A-201. Confirm with your plans, your supplier and your local code.

Sheet A-202 prepared by TakeoffMetric Editorial; no author, credential or field measurement is claimed.

Sources checked

The documents the numbers on this sheet were checked against. Nothing here is attributed to an author or a credential we do not have.

Where this page compares itself with other calculators, it describes the pages ranking on Google in the US when they were read, on September 20, 2026. Rankings change.

  1. Brick Industry Association Technical Note 10, Dimensioning and Estimating Brick Masonry Every quantity on this sheet: the brick per 100 square feet and the mortar volumes for a 3/8 in and a 1/2 in joint, for each brick designation; the sentence that the table excludes waste; the rule that one cubic foot of loose damp sand yields about one cubic foot of mortar; and the face-shell reduction for hollow brick. Opened 2026-09-20.