A deck takeoff is one division and a packing problem. Rows are deck depth over board pitch — width plus gap — rounded up: 26 rows on a 16 x 12 ft deck, 26 boards once they are cut from 16 ft stock. The same inputs give the joists, the beams, the posts and the concrete under them.

Sheet A-301
Discipline Architectural
Revised
Formula rev. 1.0.0
Checked against 5 sources

Units available: US customary / metric.

Deck size, boards and framing

Enter in feet, or type feet and inches.

Along the house, or along the beam on a freestanding deck. The boards run this way unless you pick the 45 degree layout. Type 16, 16 ft 6 in or 16' 6″.

Enter in feet, or type feet and inches.

Out from the house: this is the length of every joist. Length times depth is the deck area the board count works from.

Enter in inches, or type feet and inches.

The FACE width of your board, not its nominal name. 5.5 in is the minimum dressed dry width of a nominal 6 in NIST PS 20-20 Table 3 and 3.5 in that of a nominal 4; a composite board carries its own width on its own product sheet.

Enter in inches, or type feet and inches.

Side to side, added to the board width to make the pitch the rows are counted on. Trex asks for 3/16 in (5 mm) minimum on its own boards, 3/8 in in heavily wooded areas and never over 1/2 in. For wood decking, ask your supplier: no open source for it was found. Zero is allowed.

Order options

Attached puts a ledger on the house and one rim joist at the far side; freestanding drops the ledger and takes a rim on both sides. Flashing, hangers and ledger fasteners are not counted.

Straight boards all run the full length. At 45 degrees each course is a chord of the rectangle, the end triangles add one board width per course, and the longest piece grows — all three are computed here rather than covered by a percentage.

The spacing you are framing to. These three are the column heads of the DCA 6 joist table, offered as choices: no span is calculated here and none is printed. Joist size, species and span come from that table and your local code.

The board length your yard sells. Pieces are packed longest-first into that length; the sheet does not decide where a butt joint lands, and a joint has to land on a joist.

Advanced: beams and posts under the joists, footings and their concrete, height above grade, and the guard, assumptions

Beams and posts under the joists

Beam lines carrying the joists. On an attached deck the ledger carries one end of the joists and a beam line the other. Beam size, plies and span are set by your plans and the DCA 6 beam table.

Posts on each beam line, one footing under each. Two is the geometric minimum to hold a beam up, not a recommendation: the DCA 6 beam span table and your plans set the real number. DCA 6 asks for a 6x6 nominal post as a minimum.

Footings and their concrete

Enter in inches, or type feet and inches.

No default, on purpose: footing size belongs to the DCA 6 footing table, your plans and your local code. Type a diameter and the round-hole volume and the bag count appear.

Enter in inches, or type feet and inches.

DCA 6 asks for footings bearing on undisturbed soil at least 12 in below the undisturbed ground surface, or below the frost line, whichever is deeper. Check your local frost depth.

Yields as QUIKRETE publishes them for its Concrete Mix No. 1101 and its Fast-Setting Concrete Mix No. 1004. Ready-mix by the yard: use the concrete calculator.

Height above grade, and the guard

Enter in inches, or type feet and inches.

Deck surface to the grade below. DCA 6 requires a guard above 30 in, with 4x4 nominal guard posts as a minimum. Leave it blank and no guard line is printed.

Enter in inches, or type feet and inches.

Taken out of the guard run where the stairs land. Stringers, treads and risers are not counted.

Assumptions

Screws at every board-to-joist crossing. Trex requires two per joist on its own boards, face-screwed. With hidden clips, order per your clip's box from the crossing count.

Yours. Nothing is added until you type a number: no open source for a decking waste percentage was found.

Leave blank to skip. It prices decking boards only: joists, beams, posts, concrete, screws and railing are not priced.

Deck boards26ea

Order 26 at 16 ft

Rows
26 ea
Decking length
416 ft
Longest piece
16 ft
Deck area
192 sq ft
Joists
13 at 12 ft
Joist length
156 ft
Rim + ledger
32 ft
Beam length
16 ft
Posts / footings
2 ea
Board crossings
338 ea
Deck screws
676 ea
Footing concrete
Enter a footing diameter

    Drawings

    A-301
    Deck framing planFraming plan 16'-0″ by 12'-0″: 13 joists at 16 in on center, a ledger and one rim, 1 beam line on 2 posts and footings.LEDGER16″ O.C.13 JOISTSBEAM LINES 1POSTS ON FTG 2POS. PER PLANS
    Deck decking planDecking plan, boards running the length: 26 rows at 0'-5 11/16″ pitch, 26 boards of 16 ft, longest piece 16 ft, over 13 dashed joists.ROWS 26BOARDS 26MAX 16 FT

    Takeoff

    A-301 — material takeoff
    Item Net qty Waste Order
    Decking boards, 16 ft stock26 rows, 416 ft gross, longest 16 ft.26 ea26 ea
    Joists at 16 in on centerEach 12 ft; 156 ft total. Size per DCA 6, not by this sheet.13 ea13 ea
    Ledger + rim joistEach 16 ft. Blocking is not counted.32 ft2 ea
    Beam, 1 linePlies and size per your plans and the DCA 6 beam table.16 ft1 ea
    Posts on footings6x6 minimum per DCA 6; height per its Table 4.2 ea2 ea
    Deck screws338 board-to-joist crossings x 2. Hidden clips: per your clip's box.338 ea676 ea
    Assumptions used
    • Rows = (depth + gap) / (board width + gap), rounded up; the last row is ripped and every row runs the full length.
    • Pieces are packed longest-first into 16 ft boards: a length budget, not a joint layout. Butt joints must land on a joist.
    • Joists = length / 16 in, rounded up, plus one: both end joists included. Blocking is not counted, and no span is calculated.
    • 2 screws per board-to-joist crossing (Trex requires two per joist for its own boards, face-screwed).
    • Footing concrete needs a diameter: there is no default. The DCA 6 footing table, your plans and your local code set it.
    • No waste is added: the sheet orders what it counted until you type your own percentage.
    Order26 at 16 ft

    Rows, then the boards you actually carry home

    Rows: how many times the board pitch fits across the depth. Boards: how many pieces of the length your yard sells it takes to cut those rows. The default deck is 16 ft along the house by 12 ft out from it, boards 5.5 in wide with a 0.1875 in gap, so the pitch is 5.6875 in and the depth plus one gap is 144.1875 in. That division gives 25.352: 26 rows, the last one ripped narrow.

    Each row is 16 ft long, so the deck wants 416 lineal feet of decking — still not an order. At 16 ft stock every row is one board, 26; at 8 ft stock every row takes two, 52; on a square 8 x 8 ft deck the 17 rows pair up two to a board, 9.

    The gap belongs to your board, not to a calculator

    Gapping is quoted here as what it is, one manufacturer's instruction for its own boards: the minimum required width-to-width gapping is 3/16" (5 mm), 3/8 in in heavily wooded areas, no gapping should ever exceed 1/2" (Trex, 2026 Decking Installation Guide). The 3/16 in minimum gap, the 3/8 in for heavily wooded areas and the 1/2 in ceiling are Trex's, for Trex composite boards, and they are shown with the product name. No open source was found for the gap of wood decking: ask your supplier. Closed tight at zero, the default deck takes 27 rows instead of 26.

    The width in the form is a face width, not a nominal name. It opens on 5.5 in because that is the minimum dressed dry width of a nominal 6 in NIST PS 20-20, Table 3, where a nominal 4 reads 3.5 in. Those are standard minimums for softwood lumber, not the size of a product: a composite board carries its own width on its own sheet, and typing it in is the point of the field.

    Forty-five degrees is geometry, not a percentage

    Turn the boards to 45 degrees and each course becomes a chord across the rectangle, every piece carrying one extra board width because the cuts are measured long point to long point. That is 42 courses and 424.3 lineal feet here, against 26 rows and 416 ft straight — while the net is unchanged, 192 sq ft over a 5.6875 in pitch being 405.1 lineal feet either way. A 45 degree layout is computed, not surcharged. Net lineal footage is the same as a straight layout (deck area over the board pitch); what actually changes is the end triangles - one extra board width on every course - the longest piece, and how badly the pieces fit your stock length. All three are counted here, so no extra waste percentage is invented.

    The longest piece hurts more than the footage. Straight, nothing exceeds 16 ft; at 45 degrees the longest course here is 17.43 ft, over a 16 ft board, so the sheet warns and the packing splits it: 27 boards at 16 ft, or 22 at 20 ft with nothing jointed.

    Of the five pages we could read, one offers a 90 / 45 degree selector and tells its reader a diagonal layout adds another 10 to 15 % of waste. That is its sentence, not a figure this sheet uses: the triangles, the longest piece and the stock-length mismatch are counted.

    Pieces, not lineal feet

    Lineal feet divided by a board length is not a board count. The sheet packs the cut list longest first into the stock you chose, and a piece longer than the stock becomes whole boards plus a remainder. A 20 ft deck ordered in 12 ft boards takes 52 of them, each row a board and an offcut. The cut list is a length budget, not a joint layout. Pieces are packed into the stock length you chose, longest first; the tool does not place butt joints over joists, and they have to land on one.

    Waste starts at zero. No open source for a decking waste percentage was found, and the percentages on the pages we read are those pages' own defaults, so this sheet asks for your number instead of printing one.

    The frame under the boards

    Joists are that division turned ninety degrees: length over spacing, rounded up, plus one for the joist at the far end. 192 in over 16 gives 13 joists of 12 ft, 156 lineal feet; at 24 in on center it is 9, at 12 in 17. Those three spacings are the column heads of the joist table in DCA 6, offered as choices only. No span is calculated and none is printed. Joist, beam, post-height and footing-size tables belong to DCA 6 and are linked, never reproduced. DCA 6 is a prescriptive guide based on the IRC: your local code governs.

    An attached deck takes a ledger and one rim joist, 16 ft each; freestanding drops the ledger and takes a rim on both sides; with no ledger to hang from, picking it with a single beam line raises a question rather than a number. Posts are beam lines times posts per line, and every post gets a footing. Two per beam is the geometric minimum to hold one up, not a recommendation: DCA 6 sets post size at 6x6 nominal minimum with its height in Table 4, and its beam span table sets how far apart they stand.

    Screws follow the crossings, not the boards: 26 rows over 13 joists is 338 crossings, 676 screws at the Trex figure of two per joist. At 24 in on center, 234 crossings and 468 screws; a 45 degree course meets a joist less often, so the diagonal default drops to 233 and 466. Hidden clips are not counted for you: the crossing count is printed, your clip's box gives the rest.

    Footings, and the concrete that goes in them

    There is no default footing diameter here, deliberately: size comes from the footing table in DCA 6, from your plans and from your local code, so the concrete line reads enter a footing diameter until you type one. Depth opens at 12 in because DCA 6 asks for footings bearing on undisturbed soil at least 12 inches below the undisturbed ground surface or below the frost line, whichever is deeper.

    With a diameter typed in, a footing is a cylinder: pi over four times diameter squared times depth. 2 footings 12 in across and 12 in deep are 1.571 cu ft of concrete, 3 bags at the 0.6 cu ft QUIKRETE publishes for an 80 lb bag of Concrete Mix No. 1101; the other two choices are its 60 lb bag and the 50 lb Fast-Setting Mix No. 1004. Round holes only: for a square footing or a pad, use the concrete calculator.

    Guards, stairs, and what this sheet will not do

    Type a height above grade and a guard line appears only where DCA 6 requires one: all decks greater than 30" above grade are required to have a guard. The run is the perimeter that needs protecting — length plus two depths when the house closes one side, twice the length plus twice the depth when it does not — less the stair opening you type. At 36 in high with a 36 in opening, the default deck needs 37 ft. Its posts are 4x4 nominal at minimum in DCA 6; pickets and rails are not counted, and below 30 in no line is printed at all.

    Blocking, hangers, fasteners other than the deck screws, stairs and railing parts are not counted. The takeoff exports to CSV and prints, and both drawings redraw from what you type.

    What this sheet does that the ones we read do not

    Six results ranked for this search when it was audited; the top one never rendered its widget for us, so every claim here is about the five pages we could read. None of the five puts decking, joists, rim and ledger, beams, posts and footing concrete in one takeoff — the closest sends its reader to a separate beam calculator and a separate concrete calculator, and one lists joists and posts in its FAQ without a form we could read. None makes the gap an editable field driving the row count. None computes a 45 degree layout as geometry with the longest piece and the packing behind it. None redraws the plan from the inputs or exports a CSV. Metric units, a stock-length selector, a waste field and a screw count exist on those pages: they are not claimed here as new.

    Sheet A-301 formula
    Rows      n  =  ceil( ( D + g ) / p )        p = board width + gap
    Courses   n  =  ceil( ( L + D ) / sqrt2 / p )      45 degrees
    Piece k      =  sqrt2 x min( u, min(L,D), L+D-u ) + board width
    Boards       =  pack the pieces into your stock length, longest first
    Joists       =  ceil( L / spacing ) + 1,  each D long
    Screws       =  crossings x your screws per crossing
    Footing      =  pi / 4 x dia^2 x depth,  bags = ceil( vol / yield )
    L, D
    Deck length along the house and depth out from it. D is the joist length.
    p, u
    Pitch, and how far a 45 degree course sits along the two edges.

    Frequently asked

    How do I calculate how many decking boards I need?
    Divide the depth by the pitch — board face width plus gap — and round up: that is the rows, each the full length of the deck. The default 16 x 12 ft deck is 144 in over 5.6875 in, 25.35, so 26 rows. Then turn rows into purchases: 26 boards at 16 ft stock, 52 at 8 ft.
    How many 6 deck boards do I need?
    A nominal 6 is 5.5 in wide at minimum dressed dry size (PS 20-20, Table 3), so with the 0.1875 in gap the rows land every 5.6875 in: 26 rows and 26 boards at 16 ft on the default deck. In nominal 4 boards, 3.5 in wide, the same deck takes 40 rows and 40 boards.
    How much material do I need to build a 12x12 deck?
    Straight boards, 5.5 in wide, 12 ft stock: 26 deck boards, 10 joists of 12 ft, a ledger and a rim of 12 ft, one beam line, 2 posts on 2 footings, 520 screws. Footing concrete waits for a diameter.
    How much is material for a 20x20 deck?
    As quantities, which is all this sheet does: 43 deck boards at 20 ft, 16 joists of 20 ft, 6 posts and footings under two beam lines, 1376 screws. Prices are yours: the price field multiplies your figure by the board count and nothing else.
    What is the 3/4/5 rule for decking?
    Pythagoras, used to square a frame: mark 3 units along one side and 4 along the other, and the corner is square when the diagonal between the marks is 5, because 9 + 16 = 25.

    Limits of this sheet

    A-301 counts material on a rectangle. It does not size a joist, a beam, a post or a footing, check a ledger connection, design a guard or price a deck. Angled and wrapped decks, picture framing, multi-level platforms and hidden-fastener yields are out of scope, and stairs are not counted. For planning and ordering: your plans and your local code govern.

    Sheet A-301 prepared by TakeoffMetric Editorial; no author, credential or field measurement is claimed.

    Sources checked

    The documents the numbers on this sheet were checked against. Nothing here is attributed to an author or a credential we do not have.

    1. National Institute of Standards and Technology American Softwood Lumber Standard PS 20-20 (Revision 1, October 2021), Table 3 The dressed widths the board-width field starts from: nominal 6 = 5-1/2 in (140 mm), nominal 4 = 3-1/2 in. These are the standard's MINIMUM dressed dry sizes, not a given product's size - a composite board carries its own width on its own sheet. The 5/4 thickness is not printed: the extraction does not separate the dry and green columns. Opened 2026-09-19.
    2. Trex Company Trex 2026 Decking Installation Guide (copy hosted by The Home Depot) One product line, named wherever it is used: the 3/16 in (5 mm) minimum side gap the board count starts from, the 3/8 in recommended in heavily wooded areas, the 1/2 in that gapping should never exceed, and the two face screws per joist behind the screw count. Not a rule for wood decking, and hidden fasteners are counted differently. Opened 2026-09-19.
    3. American Wood Council DCA 6-2015, Prescriptive Residential Wood Deck Construction Guide Prose requirements only: 6x6 minimum post, footings at least 12 in below the undisturbed ground surface or below the frost line whichever is deeper, a guard above 30 in and a 4x4 minimum guard post. Its joist, beam, post-height and footing-size tables are linked, never reproduced, and no span is printed - 12 / 16 / 24 in are the table's column heads, offered as choices. DCA 6 is prescriptive and based on the IRC: the local code governs. Opened 2026-09-19.
    4. QUIKRETE Fast-Setting Concrete Mix No. 1004 data sheet The 50 lb bag yield used by the footing bag count: 0.375 cu ft. Opened 2026-09-19.
    5. QUIKRETE Concrete Mix No. 1101 data sheet The 60 lb and 80 lb bag yields used by the footing bag count: 0.45 and 0.60 cu ft. The same row already backs the concrete calculator. Opened 2026-09-19.